HB 221 · 2026 · House · Science, Technology and Energy Committee
Utilities owning nuclear power resources
AI-generated(New Title) enabling electric utilities to own, operate, and offer advanced nuclear resources, and relative to purchased power agreements for electric distribution utilities and limitations on community customer generators.
Allows electric utilities to own and operate advanced nuclear resources, modifies net energy metering eligibility and compensation for certain customer-generators, defines 'advanced nuclear reactor,' and extends deadlines for utility requests for proposals for multi-year energy purchase agreements.AI-generated
Status
Vetoed by the governor — the override vote has not been held yet · May 28, 2026- ✓Introduced
- ✓House
- ✓Senate
- Governor
- Law
Governor's veto message
“I have questions about the impact of this legislation. I understand that this language is also attached to another bill scheduled for a conference committee and will work with the conference committee in an effort to reach an outcome that is protective of ratepayers.”
A passage from the Governor's veto message, quoted verbatim. The full message enters the record on veto day.
Analysis
This bill modifies the assessment of system benefit charges cost effectiveness.
From the bill's official ANALYSIS section.
In the bill's words
Quoted verbatim from the bill as passed by both chambers.
“"Advanced nuclear reactor" has the same meaning as that provided in 42 U.S.C. section 16271(b)(1), as amended from time to time.”
The bill defines "advanced nuclear reactor" by reference to federal law, the definition that governs which resources qualify for the higher procurement caps it creates.AI-generated
“A single net meter that shows the customer's net energy usage by measuring both the inflow and outflow of electricity internally shall be the extent of metering that is required at facilities with a total peak generating capacity of not more than [100] 250 kilowatts.”
The bill raises the capacity threshold for simple single-meter net metering from 100 to 250 kilowatts, expanding which customer-generators qualify.AI-generated
“Investor-owned electric distribution utilities may elect to develop and, no later than June 30, [2025] 2040, issue a request for proposals for multi-year agreements for energy, in conjunction with or independent of any attendant environmental attributes from electric energy sources.”
The bill extends by 15 years the deadline for utilities to solicit long-term energy contracts, keeping the purchased-power authority open through 2040.AI-generated
“any single source shall be eligible to procure an amount of energy not to exceed 1 million megawatt hours statewide, on an annual basis, except for advanced nuclear reactors as defined in RSA 374-F:2, II-a, which may procure an amount not to exceed 2 million megawatt hours on an annual basis.”
The bill grants advanced nuclear reactors double the per-source procurement ceiling available to other energy sources.AI-generated
Official record
gc.nh.gov · the authoritative source
Sponsors
- Rep. JD BernardyRClerk· Science, Technology and Energy
- Rep. Jeanine NotterRAssistant Majority Leader
- Rep. Douglas ThomasRVice Chair· Science, Technology and Energy
- Rep. Michael VoseRChair· Science, Technology and Energy
Also: Rep. James SummersR
Public testimony
No one submitted online testimony on this bill. See the record
Hearings and debates
- Jan 27, 2025Public hearingHouse Science, Technology and Energy33:11–1:31:2958m 18s
- Mar 4, 2025Full committee work sessionHouse Science, Technology and Energy10:20–43:5533m 35s
- Mar 4, 2025Executive sessionHouse Science, Technology and Energy2:51:02–2:52:241m 22s
- Mar 20, 2025Floor debateHouse floor6:47:43–7:04:5017m 7s
- Apr 1, 2025Public hearingSenate Energy and Natural Resources21:31–1:07:0545m 34s
Timestamps locate where this bill is taken up in the chamber's YouTube stream.
Votes
yeanay- Mar 4, 2025HouseCommittee report· regular calendar: Ought to Pass9–8Overall53% yea
- Mar 20, 2025HouseRoll callLay HB221 on Table (Rep. N. Germana)Failed151–193Overall44% yea
- Mar 20, 2025HouseRoll callOught to PassAdopted195–151Overall56% yea
- May 15, 2025SenateCommittee report: Rereferred to Committee5–0Overall100% yea
- May 15, 2025SenateVoice voteRereferred to Committeeadopted
- Overall80% yea
- Resulting text: Bill as amended by the Senate
- Apr 23, 2026HouseVoice voteHouse Non-Concurs with Senate Amendment 2025-3044s and Requests CofC (Rep. Vose)adoptedResulting text: Bill as adopted by both chambers
- Apr 23, 2026SenateVoice voteSen. Carson Accedes to House Request for Committee of Conferenceadopted
Legislative history
- Jan 8, 2025HouseIntroduced 01/08/2025 and referred to Science, Technology and Energy HJ 2 P. 11
- Jan 27, 2025HousePublic Hearing: 01/27/2025 09:30 am LOB 302-304
- Mar 4, 2025HouseFull Committee Work Session: 03/04/2025 10:30 am LOB 302-304
- Mar 4, 2025HouseExecutive Session: 03/04/2025 01:00 pm LOB 302-304
- Mar 4, 2025HouseMajority : Ought to Pass 03/04/2025 (Vote 9-8; RC)
- Mar 10, 2025HouseMinority : Inexpedient to Legislate
- Mar 20, 2025HouseLay HB221 on Table (Rep. N. Germana): MF RC 151-193 03/20/2025 HJ 9 P. 82
- Mar 20, 2025HouseOught to Pass: MA RC 195-151 03/20/2025 HJ 9 P. 84
- Mar 20, 2025SenIntroduced 03/20/2025 and Referred to Energy and Natural Resources; SJ 9
- Apr 1, 2025SenHearing: 04/01/2025, Room 103, SH, 09:20 am; SC 15
- May 15, 2025Sen: Rereferred to Committee, 05/15/2025; Vote 5-0; CC; SC 21A
- May 15, 2025SenRereferred to Committee, MA, VV; 05/15/2025; SJ 13
- Jan 7, 2026SenCommittee Report: Ought to Pass with Amendment # 2025-3044s, 01/07/2026; Vote 4-1; CC; SC 46
- Jan 7, 2026SenCommittee Amendment # 2025-3044s, AA, VV; 01/07/2026; SJ 1
- Jan 7, 2026SenOught to Pass with Amendment #2025-3044s, MA, VV; OT3rdg; 01/07/2026; SJ 1
- Apr 23, 2026HouseHouse Non-Concurs with Senate Amendment 2025-3044s and Requests CofC (Rep. Vose): MA VV 04/23/2026 HJ 11 P. 82
- Apr 23, 2026HouseSpeaker Appoints: Reps. Vose, D. Thomas, Bernardy, Notter 04/23/2026 HJ 11 P. 82
- Apr 23, 2026SenSen. Carson Accedes to House Request for Committee of Conference, MA, VV; (In recess 04/23/2026); SJ 10
- Apr 23, 2026SenPresident Appoints: Senators Avard, Pearl, Watters; (In Recess 04/23/2026); SJ 10
- Apr 30, 2026HouseConference Committee Meeting: 04/30/2026 10:00 am GP 229
- May 14, 2026SenConference Committee Report Filed, # 2026-1774c; 05/14/2026
- May 14, 2026SenConference Committee Report # 2026-1774c, Adopted, VV; 05/14/2026; SJ 12
- May 14, 2026HouseConference Committee Report 2026-1774c: Adopted, VV 05/14/2026 HJ 13 P. 43
- May 14, 2026SenEnrolled Adopted, VV, (In recess 05/14/2026); SJ 13
- May 14, 2026HouseEnrolled (in recess of) 05/14/2026 HJ 13 P. 147
- May 22, 2026HouseVetoed by Governor Ayotte 05/22/2026
Coverage
- Ayotte Signs 16 Bills Into Law, Vetoes OneInDepthNH · May 22, 2026
HB 221, enabling electric utilities to own and operate advanced nuclear resources, was the one bill Ayotte vetoed, citing concerns about the impact on ratepayers.AI-generated
- Nuclear power dominated energy debate in Concord. Two bills now head to Ayotte's desk.NHPR · Jun 10, 2026
The article discusses Ayotte's veto of HB 221, which would have created a pathway for utilities to enter agreements with advanced nuclear reactors and expanded net metering.AI-generated
- Nuclear power dominated energy discussions this session. A pair of bills now head to Ayotte's desk.New Hampshire Bulletin · Jun 10, 2026
The piece recounts Ayotte's veto of HB 221 and its net metering and advanced nuclear provisions amid the session's energy debate.AI-generated
Background reading
Evergreen reading on the policy area — spanning perspectives — not coverage of this specific bill.
U.S. Department of Energy, Office of Nuclear Energy — Federal overview of what advanced small modular reactors are, how they differ from conventional plants, and their potential uses.AI-generated
- Clean EnergySupporters
Nuclear Innovation Alliance — Advocacy group's case that advanced nuclear can provide carbon-free, always-available power alongside wind and solar.AI-generated
Utility Dive — Opinion piece arguing the cancelled NuScale/UAMPS project illustrates the cost and schedule risks facing small modular reactors.AI-generated
- Nuclear WasteCritics
Union of Concerned Scientists — Explains the unresolved problem of storing and disposing of long-lived radioactive spent fuel from nuclear plants.AI-generated
New Hampshire Bulletin — Reports on New Hampshire legislation letting utilities own generation and the ratemaking debate over who bears the risk and cost.AI-generated
New Hampshire Public Radio — Examines the state's push for more nuclear power, the role of Seabrook Station, and how new reactors might fit the grid.AI-generated
Documents (PDF)
- Introducedversion
- As Amended by the Senateversion
- Adopted by both chambersversion
- Chaptered (final law)version
- Amendment 2025-3044samendment
- Amendment 2026-1774CofCamendment
- Governor's veto statementveto